Shear Wall Strengthening For Hill House (Phase 2) | 26/01/2016

An 11 storey office block in North London is being converted into luxury residential apartments. Following the successful delivery of phase one of the project, Heyne Tillet Steel awarded Fibrwrap UK a further package of shear wall strengthening works at Hill House. Phase 2 of this extremely prestigious project for Fibrwrap UK is the strengthening of shear walls in the two main cores of this multi storey building. Using Tyfo Supr-Anchors to pass through slabs and staircases this extremely complicated FRP design has culminated in nearly 4000m2 of Tyfo Fibrwrap Carbon Fibre Strengthening System. We were very proud to be working on such a large project and believe this could be the largest FRP strengthening of a building in the UK to date.

Project: Hill House.

Client: HG Construction London.

Contract Duration: 16 weeks

Scope of Works: Shear Wall Strengthening.